This is the working surface: header, four money stats, then the budgeter. Figures are examples, not live accounting. Your real jobs are private to your account.

Create accountSign in

205 Spruce St

Sample
Multi-unitActive

Phase is the crew's place on the job (planning → complete). Percent complete is not a vibe slider — it is spent ÷ estimated on these budget lines. Remaining to complete is estimated − spent.

Spent

$97,450

Sum of line spent

Remaining to complete

$87,550

Estimated − spent

Percent complete

53%

Dollar progress: spent ÷ estimated

Estimated total

$185,000

Sum of line estimates

Budget lines

Rehab line items — demo, trades, finishes. Estimated vs spent vs remaining. The four numbers above are this table, rolled up.

LineEstimatedSpentRemainingComplete
Demolition$12,000$12,000$0100%
Framing & structure$28,000$22,400$5,60080%
Electrical$18,500$9,200$9,30050%
Plumbing$16,000$11,800$4,20074%
HVAC$14,500$3,100$11,40021%
Kitchens & baths$42,000$18,750$23,25045%
Flooring & finishes$31,000$8,400$22,60027%
Permits & contingency$23,000$11,800$11,20051%
Project total$185,000$97,450$87,55053%